South Washington and South Maple Intersection Pedestrian Accessibility

​Status


In-Progress (Summer 2021)
Construction advertisement expected in Summer 2021 following VDOT approval. Construction should begin in Fall 2021 and be completed in Spring 2022.  

​About the Project


Pedestrian accessibility improvements at South Washington Street and South Maple Avenue intersection. This project includes a new signal, ADA curb ramps, crosswalks, and pedestrian push buttons. View final design plans (PDF). 

South Washington and South Maple Intersection rendering


Project Location






Funding

The S Washington and S Maple Intersection Pedestrian Accessibility project is funded through Six Year Improvement (SYIP) funds. 



Schedule


  • Engineering Design: Summer 2019
  • Advertisement: Summer 2021
  • Construction Start: Fall 2021
  • Project Completion: Spring 2022

​Public Meetings


May 18, 2017 Meeting
March 22, 2017 Meeting


Contact Information


For more information about this project, please contact Alvaro Astorga at 571-835-6795 (TTY 711).