Oak Street Bridge

Status: Design Phase

The City is beginning the design phase for the bridge replacement.

On Monday, October 21 at 7:30 p.m. at the start of the Planning Commission meeting, the City will hold a Public Information Session and Public Hearing in Council Chambers. The presentation will include the conceptual design for a new bridge structure to replace the existing Oak Street Bridge over Tripps Run. The consultants and design team from Kimley Horn will be available to hear comments and answer questions.

About the Project

Oak Street Bridge is located over Tripps Run, between S Lee Street and Timber Lane. The scope of the work is the replacement of steel beams and concrete deck. Ancillary benefits of the project are improving pedestrian accessibility and trail access point to Howard E. Herman Stream Valley Park. 

Oak Street Bridge is a simple span steel beam bridge with reinforced concrete deck and concrete abutments. In 2012, Dewberry inspectors found the bridge to be in poor condition with a bridge rating of 4 out of 10. There is severe corrosion in the steel beam webs. Timber blocking was installed at locations where steel beam webs were severely corroded. Concrete deck has spalling and numerous hairline cracks with some exposed rebar.

The bridge has been on a yearly inspection cycle since 2012. The rating has not changed and there have been no major changes from the 2012 condition. Each annual inspection recommends replacing or repairing the steel beams and concrete deck immediately. 

Draft Concept

Project Location



Funding


The estimated cost for planning, design, and construction is $2,600,000. This project is partially funded through Regional Surface Transportation Program (RSTP) funds and administered from the Virginia Department of Transportation (VDOT). The City is seeking additional grant funding to complete the budget funding gap. 

Contact Information


For more information, please contact Sue Long at 703-248-5350 (TTY 711).